Industrial / FMCG
Industrial Facility Commissioning
₦1.8BProgramme Value
24 monthsDuration
West Africa, Europe, East AfricaGeography
The Challenge
Major FMCG client required end-to-end delivery for manufacturing facility commissioning, the eleventh in a multi-site programme across five countries. 40+ stakeholders, contractor underperformance, NEC4 complexity.
5
Key Result'Smoothest in 5 years'Client VP assessment of facility launchOur Approach
1
Applied HAZOP and process safety methodologies.
2
Restructured delivery plan.
3
Applied LOPA risk scoring.
4
Managed commissioning through Environment Agency sign-off.
Outcomes
Result 1'Smoothest in 5 years'Client VP assessment of facility launch
Result 22% of budgetDelivered within budget tolerance
Result 394%User adoption of operational platform within 3 months
Result 4Standard adoptedHandover protocols adopted as standard